This is the second notice issued by the National Energy Administration for Jiuquan wind power construction after March 27th. Energy expert Zhou Dadi said that the Energy Bureau issued two "tokens" in more than one month, which indicates that the country has started to clean up the construction order and regulate the healthy development of the "12th Five-Year Plan" wind power industry.
The national "token" can't hold the impulse of local construction
It is understood that Jiuquan 1000-kilowatt wind power base is a national key project for wind power planning and construction. The first-phase construction of more than 500 million kilowatts of construction projects has been basically completed. At present, the second phase of the project is beginning to be demonstrated, and issues such as market absorption and construction management are not yet clear.
On March 19, the Jiuquan Energy Bureau issued the “Notice on Issues Related to the Second Phase Construction of Jiuquan Wind Power Baseâ€, and issued “construction missions†for 2011 to related companies, proposed “progress requirementsâ€, and “specific models†for wind power. Arrangements are made to threaten companies that cannot complete their development tasks and the development of the remaining indicators is suspended. The most surprising thing is that the "Notice" also pointed out that "Jiuquan Wind Power Equipment Manufacturing Industrial Park is a national high-tech industrialization base for wind power equipment determined by the Ministry of Science and Technology... Under the same conditions, in principle, the wind power equipment produced in this park will be preferred for competition. ."
In response, the National Energy Administration issued the “Circular on the Construction of the Second-phase Project of a 10 Million-Kilowatt-class Wind Power Base in Jiuquan†on March 27 (Guineng New Energy [2011] No. 104), which will correct the practices of the Jiuquan Energy Bureau. Explicitly stated that "local governments and departments at all levels must not arrange the scale of wind power construction and allocate the right to confirm the development of the project to the enterprise, and they are not required to administratively require the enterprise to complete the construction tasks."
The National Energy Administration requires that “the construction of wind power should strictly implement the management procedures for capital construction projects, attach great importance to the pre-project work, and implement the conditions for power grid access, market absorption and environmental protection, and must not start construction without approval.â€
In particular, in response to the requirements of the Jiuquan Energy Bureau in bidding for wind power equipment, the National Energy Administration emphasized that “local governments and anyone must not interfere with the wind power construction market, and must not require companies to purchase local equipment or put forward restrictions on local protection of the place of production. â€
However, the notice of the National Energy Administration failed to prevent the impulse of local government construction. On April 27, the Jiuquan Energy Bureau reissued the "Circular on Enhancing the Pre-2011 Work of the Second Phase of the Jiuquan Wind Power Base Project", and issued 26 "Government Task Schedules" for the Guodian Gansu Company and other 26 companies. On the other hand, in disguised form, all companies are required to “support local economic development and strive to achieve a win-win situation for local enterprisesâ€.
The Energy Bureau twice demonstrated the resolve of the industry
On May 9, the National Energy Administration issued the second "token", the "Notice on the requirements for the construction of the Jiuquan Wind Power Base," and put forward "severe criticism" of the above-mentioned actions of the Jiuquan Energy Bureau.
"Notice" clearly requires that: "The Jiuquan Wind Power Base Phase II project development plan and project owner arrangements must be reviewed and approved by the national energy authority." "Without the approval of the national energy authority, no on-site construction shall be carried out and no Jiuquan wind power shall be provided. The project within the base will be split into 50,000 kilowatts and approved."
The “Notice†proposed to “further regulate the order of wind power construction†and reaffirmed that wind power construction “should strictly comply with the requirements of the national capital construction project, and strictly enforce the system of legal person responsibility, bidding and construction supervision, etc. No unit or individual may interfere with the market. Or interfere with the normal production and operation of the company."
The "Notice" emphasized that "without the approval of the national energy authority, any wind power project that is started ahead of time, the State Grid Corporation of China shall not be allowed to access the grid, nor may it enjoy the tariff subsidies of the National Renewable Energy Development Fund. It is undertaken by the project unit and the department that has authorized the construction of the project without authorization.†In this severely worded “Noticeâ€, the National Energy Administration pointed out sharply that there was a series of problems in the construction of the Jiuquan wind power base. The scope of off-grid accidents such as off-grid, crew speeding, and fire accidents exposed the problems of market, technology, and management in the construction and operation of wind power."
“These problems are obviously also one of the important reasons that prompted the National Energy Administration to resolve to clean up the Jiuquan wind power base.†Zhou Dadi, vice chairman of the China Energy Research Institute, said in an interview with reporters that some problems in the Jiuquan wind power base exposed the entire With the common problems existing in the rapid development of the industry, the National Energy Administration issued two tokens in a row, not only to rectify the construction of Jiuquan Wind Power, but also to take an important measure to ensure the healthy development of the entire wind power industry.
Control "building rhythm" to promote "healthy development" of wind power
The reporter noticed that the National Energy Administration clearly stated in the second “Notice†that “the rational pace of the construction of wind power bases should be controlled.†What impact will this have on the rapidly developing wind power industry in recent years?
It is understood that during the “Eleventh Five-Year Plan†period, wind power installed capacity doubled for five consecutive years, with a cumulative installed capacity of 44,733.29 MW, ranking first in the world. However, the rapid development of the entire industry has also exposed some problems. For example, some local wind power projects have been “divided into zero†to bypass national approvals, wind power equipment tenders have been “protected†for the protection of local interests, and wind power construction speed exceeds grid construction plans. However, it is difficult to connect to the grid and the technical quality of wind turbines frequently occurs.
"The development of wind power in China requires speed and quality." Shi Lishan, deputy director of the New Energy and Renewable Energy Division of the National Energy Administration, said in an interview that "especially for the construction of large-scale wind power bases, we must adhere to overall planning, gradual and orderly development. Principles, continuously sum up experience, improve technology and management, and achieve unity of economic and social benefits."
Zhou Dadi believes that wind power construction is a systematic project. From the policy point of view, policy support such as national electricity price subsidy is needed; technically speaking, it is necessary to support power grids to absorb capacity; from the market, it is necessary to create a fair competition for enterprises. surroundings. He said that the National Energy Administration pointed out two tokens issued by Jiuquan Wind Power Base and clearly stated that “reasonable control of the construction pace of wind power bases†is of great significance to regulating wind power construction order and promoting the healthy development of the entire wind power industry.
Electric tracker head products under this category are characterized by advanced drive motor, strong power, maintenance free and large torque. Strong climbing ability, strong traction and power. Ensure that the car can still drive smoothly on uneven roads and slopes, and the service life of the battery is longer.
Electric Tractor Head,Battery Operated Tractor And Trailer,Tractor Battery Operated,Battery Operated Tractor
Jiangsu Anli Electric Vehicle Co. Ltd , https://www.anlitractor.com